PBO Alto Construction Costs Report
October 1, 2026
This morning, the Parliamentary Budget Officer (PBO) released a cost analysis report on ALTO, the federal Liberal government’s proposed high-speed rail line between Toronto and Quebec City. According to the PBO, ALTO is likely to cost substantially more than the government’s public estimates – a conclusion shared by me and others who have examined the government’s case for ALTO.
The PBO report is available here: https://www.pbo-dpb.ca/en/publications/RP-2627-009-C–canada-eastern-corridor-high-speed-rail-cost-analysis-using-global-data–train-grande-vitesse-corridor-est-canada-analyse-couts-aide-donnees-mondiales
—–o0o—–
- Global cost of constructing ALTO is $75 billion – $113 billion (not $60 – $90 billion). The midpoint of this range ($94 billion) is higher than the highest-range estimate given by the Government. This equals a 25% increase in estimated costs, as the midpoint of the new estimate ($94 billion) to the midpoint of the Government’s earlier estimate ($75 billion is the midpoint between $60 and $90 billion).
—–o0o—–
- This report deals only with construction costs. Operating costs and ridership projections are separate, and relevant. The following statement is made on p. 8 of the PBO report (emphasis added by me):
The motivation for HSR projects typically includes the economic benefits to business and pleasure travellers of shorter, more predictable, and ideally cost-effective, travel as compared to travelling by road or air – as well as the environmental benefit of reducing fuel consumption and infrastructure depreciation accordingly. PBO is currently compiling information about regional travel volumes across these different modes of transport as the basis for this subsequent study.
And in the summary on p. 6:
This report is the first of a two-part assessment of the viability of the proposed HSR line; a subsequent report will examine whether projected ridership is sufficient to support the system’s operations.
—–o0o—–
- Total cost must include operating costs, which are likely to be between $64 – $69 billion. Given that only construction costs are taken into account, the huge operational costs that were leaked to the Globe and Mail (published on August 31, 2026) should continue to be added to the new, elevated construction-cost estimate. The leak to the Globe shows that the cost to maintain and operate the rail line would be somewhere between $64 and $69 billion. Added together, the operating costs and the construction costs lead to a range of $139 billion – $182 billion, with a midpoint of $160.5 billion.
—–o0o—–
- Diverting the rail line south to Kingston would add roughly $4.4 – $6.6 billion to construction costs, leading to a new project total of $143.4 – $186.6 billion.
The PBO refuses to assign a cost to the proposed diversion, but notes on p. 14 that
While this report does not estimate the cost of a Kingston route as announced on June 22, 2026, it should be noted that the more sensitive nature of the Kingston ecology as well as its denser population and later planning start vs the baseline route are all significant risks that may place the Eastern HSR project at greater risk of U.K. and U.S. style cost escalation.
I have based the additional cost on the PBO’s twin assertions that:
(a) the diversion would add 50 km to the train route (p. 15); and
(b) construction costs per km = $88 million – $133 million (p. 16).
Please note that the PBO is explicit that the $88 – $133 million per km is a base estimate; tunnels, bridges and viaducts are significantly more expensive, and the PBO clearly assumes that at least some bridges and viaducts would be needed along the 50 km expansion, meaning that the $133 million-per km estimate is probably unduly optimistic.
The $4.4 – $6.6 billion estimate is based on multiplying the per-km construction costs by 50 km.
—–o0o—–
- Factors based on local opposition could cause costs to go up significantly. The PBO’s report is vague on what exactly is meant by this, but the matter is clearly taken seriously. On p. 17, the PBO writes,
[In] scenarios where Bills C-5 and C-15 are not sufficient to contain costs related to process issues (e.g., environmental or stakeholder challenges, etc.) as was observed in the United States, and/or management-related delays extended the project, as was observed in the United Kingdom, costs could rise significantly beyond the PBO-estimated range. The difference between this adverse scenario and the reference scenario primarily reflects institutional and cultural factors, more so than geographic and technical factors, as the cost overruns observed in the U.K. and U.S. are seen to be largely unrelated to engineering challenges.
Elsewhere in the report, the following explanation is provided:
Both the fast-tracking of large projects through Bill C-5 (One Canadian Economy Act, June 26, 2025) and the High-Speed Rail Network Act, enacted through Bill C-15 on March 26, 2026, aim to mitigate some of these potential difficulties related to project delay. The legislation declared that the network is to work for the general advantage of Canada, deemed the required line-location approval as given, and consolidated review under a single Impact Assessment Act process. It also altered land acquisition, including a right of first refusal for Alto and amended the federal Expropriation Act.
While the passage of those bills can be expected to have diminished legal risks, the prospect of court challenges or other litigation remain risks to construction timelines. Moreover, even if the bills survive legal challenges, it cannot be assumed that they have correctly addressed the potential drivers of cost escalation.
Since the objective of project opponents is to force the government to abandon ALTO, it is reasonable to assume that they will investigate how best to use court challenges to tie up the expropriation process and to undermine the streamlining efforts laid out in C-5 and C-15.
—–o0o—–
- The report assumes that construction is becoming less efficient and more costly every year, and that this will drive up construction costs if there are any delays.
Frankly, I was astonished by this claim—and by the casual assumption that there is no point in addressing the underlying problem, which goes against every normal economic process (where costs continue to fall over time). All I can do is to quote this extraordinary claim verbatim:
The inclusion of a start date in the estimation also merits additional comment. For each later year that the project starts construction, $1.5 billion ($1.1 to $2.0 billion, in real 2024 CAD) is added to the overall cost. While productivity improvements tend to lower the cost of goods and services, some sectors of the economy (in most countries) do not benefit as much. Illustrative is the Highway, Street and Bridge Construction in the U.S. Productivity has been trending downward since 2009, and by 2024 was 25 per cent lower than in 2002.17 The construction industry in general has not been able to achieve productivity growth similar to that in the rest of the economy. This signals that the start date of construction can be a factor in how much the project will reflect these competing pressures.
Surely a 25 percent decline in productivity merits further investigation and remediation, rather than a race to construct quickly, against a trend that is casually assumed to inevitably project out ad infinitum? Surely, as well, is it not likely that regulatory factors lie at the heart of this decline in productivity? So wouldn’t it make more sense to address these first, and to start construction on ALTO-style megaprojects after the problem has been corrected?
Moreover, is it the case that the productivity decline has been even more precipitous in Canada? (It seems odd that an American statistic is being cited for a project that is planned for Canada.)
—–o0o—–
- The PBO projects a worst-case scenario of over $240 billion.
The worst-case scenario is not the likeliest scenario, but it should nevertheless be included in the discussion, so that Canadians embark on this infrastructure project with eyes wide open. On p. 21, the PBO notes:
Uncertainty in the estimation can be gauged by bootstrap replication. Using a bootstrap methodology, an upper-bound cost with 16 per cent tail probability would give a total cost $115 billion (versus $113 billion using the parameters of Table A1). Moving to an upper-bound cost with 2.5 per cent tail probability gives $243 billion. This implies that based on these international experiences, there is a 1 in 40 chance that costs would reach or surpass a total of $243 billion.
—–o0o—–
- The worst-case scenario is for construction costs only. To this must be added the operating costs leaked to the Globe and Mail.
The operating costs leaked to the Globe and Mail were $64 – $69 billion. Therefore the total cost of ALTO, in a worst-case scenario that has a 1-in-40 chance of happening, is between $307 and $312 billion.
—–o0o—–
- The per-citizen and per-family costs of Alto, as measured by the PBO, are outlined below.
There are 40 million Canadians, and therefore, there are, notionally, 10 million Canadian families. The per-citizen and per-family costs of Alto are therefore:
- PBO’s lowest-cost reference-range estimate ($75 billion):
Per citizen: $1,875 Per family of four: $7,500
- PBO’s high-cost reference-range construction cost estimate ($113 billion):
Per citizen: $2,825 Per family of four: $11,300
- Total construction cost plus operating cost ($160.5 billion). This is PBO’s mid-range construction cost ($94 billion) + mid-range operating cost ($66.5 billion, as leaked to the Globe and Mail):
Per citizen: $4,012 Per family of four: $16,050
- Additional cost of diverting the rail line south to have a stop in Kingston (mid-range estimate is $5.5 billion):
Per citizen: $137.50 Per family of four: $550
- Worst-case cost scenario—4% probability, according to PBO ($240 billion in construction costs)
Per citizen: $6,000 Per family of four: $24,000
- Worst-case construction cost scenario, plus mid-range projected operating costs ($309.5 billion)
Per citizen: $7,737.50 Per family of four: $30,950
—–o0o—–
Scott Reid
My speech in the House of Commons on Thursday February 26, 2026:
As currently proposed, this high-speed rail network would run between Ontario and Quebec, with seven proposed stops: Toronto, Peterborough, Ottawa, Montreal, Laval, Trois-Rivières, and Quebec City.
The Liberal government has announced that the first segment of this project would operate between Ottawa and Montreal, with the intention of beginning construction as early as 2029.
I have serious concerns regarding this project, which I would like to outline below.
—–o0o—–
Divided communities and loss of local road connections:
High-speed rail requires a fully dedicated corridor with no level crossings. At this stage, it remains unclear where the rail line would pass through local communities. A very rough predictive map is available, but there is no guarantee that it would be followed (indeed, two separate options are proposed, for the part of the map running through Frontenac and Lanark Counties). The map can be seen HERE.
This is deeply concerning, because high-speed rail is incompatible with level crossings. There are therefore two ways of constructing a high-speed rail line:
Create a bridge or underpass at where the rail line encounters an existing road; or
Turn the road into two unconnected dead ends, so that people on either side must now drive to the nearest overpass in order to travel past where the rail line has been placed.
As a practical matter, installing literally hundreds of bridges or underpasses at all of the places, between Quebec City and Toronto, where the new rail line crosses local roads would cost billions of dollars. Since the project is already projected to cost $60 – $90 billion, it is likely that one cost-saving measure would be to have as few bridges / underpasses as possible.
To give an idea just how expensive the bridges and underpasses would be, I did an online search for the cost of recent overpasses, installed in different parts of Canada, over rail lines. In urban areas, where the roads can be four lanes wide and there may be a need for other expensive features, recent costs have been as much as $190 million [Pitt Meadows, BC], $180 million [Edmonton] and $200 million [Holdem Ave. in Burnaby, BC]. In rural areas, the costs are lower, but still significant, and would likely be above $20 million per road.
Therefore, it is far more likely that most such intersections will be dealt with by creating dead ends, and that only major roads will receive an overpass or underpass.
In towns that are bisected by the rail line, entire neighbourhoods could be geographically divided, significantly disrupting daily life. A short drive across a local road to visit neighbours or commute to work could instead require lengthy detours, simply due to severed secondary road access. The situation would likely be worse in rural and agricultural areas, as the drive between overpasses would likely be significantly greater.
Among the considerations worth taking into account are lost access to lake and recreational properties when only a single existing road crosses the rail line, and the fact that emergency services such as fire, police and paramedics would become significantly worse for numerous residential locations.
—–o0o—–
Environmental concerns:
It should be noted that a project of this magnitude would cause significant disruption to local environments and habitats within the community.
Construction at this scale would inevitably result in the destruction or fragmentation of existing ecosystems and agricultural lands.
Furthermore, high-speed trains operating at velocities of up to 300 km/h, as proposed for Alto’s high-speed rail system, would generate substantial noise and ground vibrations. These impacts would displace wildlife and permanently compromise the viability of nearby natural habitats, as well as agricultural operations in the surrounding area.
—–o0o—–
The project would result in significant expropriations:
The best models for the kind of expropriations of private property, in the name of federal megaprojects, are the Pickering Airport project, near Toronto, and the Mirabel Airport project, near Montreal. The Pickering project resulted in the expropriation, in 1972, of 18,600 acres of land (mostly farmland). The Mirabel project resulted in the expropriation of 96,000 acres of land. Many family farms were destroyed, and many lives were ruined.
Ultimately, both projects were abandoned, after the airports turned out to be more expensive than anticipated, and to have much less demand than anticipated—both of which are problems that are likely to be replicated in the case of the Alto project.
But because it is relatively inexpensive (and because no construction can occur until expropriation is completed), expropriation always occurs first—even in the case of projects that are ultimately abandoned, as these ones were.
—–o0o—–
Bill C-15 or the Budget Implementation Act:
Bill C-15 proposes to make it easier for the government to expropriate land for the Alto rail project. It also includes speeding up approvals under the Impact Assessment Act, as well as easing the process by which the government can expropriate land for the railway.
I strongly object to legislative measures that erode landowner protections or authorize below-market valuations in eminent domain and expropriation proceedings.
—–o0o—–
The Alto project would result in the loss of existing rail service:
The proposed high-speed rail would not stop in rural or small-town areas. There would be no stops in either Lanark or Frontenac County. Residents in the southern portion of the riding would need to travel as much as two and a half hours just to access a station stop in Ottawa or Peterborough, and no part of the riding would be less than an hour from the nearest high-speed rail station.
It is highly likely that the high-speed rail service would result in the end of the existing Via Rail service that passes through Kingston, Smiths Falls, and other centres along the existing Via rail line. The promoters of the Alto project may suggest otherwise, but as a practical matter, all commuters who are seeking to go from Montreal or Ottawa to Toronto will choose the faster Alto train, and will thereby strip away at least three quarters of Via’s passenger traffic.
This will render Via Rail financially untenable (in 2023—the most recent year for which I was able to find financial figures–Via Rail had revenues of $430.7 million and expenditures of $812.5 million. The loss of the greater share of the company’s revenues would inevitably lead to the cessation of service.
In-person consultations (no registration required):
Alto is currently conducting public consultations on the proposed high-speed rail project. I strongly encourage you to participate by attending an in-person or virtual session, or by submitting your comments through their online consultation form. Don’t be shy about expressing your concerns!
Date: Wed Feb 18, 2026
Time: 11am-3pm & 5-9pm
Location: Storrington Lions Hall
Date: Wed Mar 4, 2026
Time: 11am-3pm & 5-9pm
Location: Perth Lions Club
Virtual English Sessions:
Fri Feb 20 at 12:00pm
Mon Feb 23 at 7:00pm
Tues Mar 3 at 7:00pm
Virtual French Sessions:
Mon Feb 16 at 7:00pm
Tues Mar 17 at 7:00pm
The online consultation form can be seen HERE
More details on the project can be seen HERE
I remain opposed to the expansion of the Alto High-Speed Rail project and will continue to advocate for road access and the protection of our communities from unnecessary disruption.
Scott Reid MP
Lanark-Frontenac
Please consider signing my paper petition HERE
This is a paper petition and therefore hard copy signatures are required. Once signatures are collected, please drop off or mail the original copies to my office.
Petitions can be mailed to the following address:
Scott Reid, MP
House of Commons
Ottawa, ON
K1A 0A6
NOTE: mail sent to your Member of Parliament is free of charge.
My first House of Commons electronic petition on this topic closed on May 28, 2026 with 17,531 signatures.
My second House of Commons electronic petition (e-7458) on this topic closed on September 25, 2026.



